Free templates / Construction daily log
Construction daily log template
A two-page superintendent's daily report on US Letter: weather, manpower by company and trade, equipment, work performed, deliveries, inspections and tests, visitors, delays, safety and instructions received.
The daily log is the record nobody reads until there's a claim, a delay dispute or an accident. Then it's the first thing everyone asks for. A log written the same day, with numbers instead of adjectives, is worth far more than a better-looking one reconstructed a week later.
How to fill it in
- Fill it in every working day, including days when nothing happened. "No work, rain from 6 AM, site closed" is a useful entry.
- Record weather twice, morning and afternoon. Weather is the most common reason a delay claim succeeds or fails.
- Count manpower by company and trade, with hours. "Electrical: 6 workers, 8 hrs, L2 rough-in, grids C–F" beats "electricians on site."
- Write delays as facts with a cause and a time. Keep opinions about who is to blame out of the log.
- Note instructions you received, from whom and when, even verbal ones. That line often decides whether extra work gets paid.
- Sign it and file it the same day.
More detail in the guide: Construction daily log: what to record every day.
Construction Daily Log
Superintendent's daily report
Weather
Manpower on site
| # | Company | Trade | Workers | Hours | Work performed / location |
|---|---|---|---|---|---|
| 1 | |||||
| 2 | |||||
| 3 | |||||
| 4 | |||||
| 5 | |||||
| 6 | |||||
| 7 | |||||
| 8 |
Equipment on site
| # | Equipment | Owner / sub | Hours used | Hours idle | Notes |
|---|---|---|---|---|---|
| 1 | |||||
| 2 | |||||
| 3 | |||||
| 4 |
Work performed today (by area)
Deliveries and materials received
| # | Material / item | Supplier | Qty | Ticket / BOL no. | Received by / condition |
|---|---|---|---|---|---|
| 1 | |||||
| 2 | |||||
| 3 | |||||
| 4 |
Inspections and tests
| # | Inspection / test | Agency / inspector | Area | Result |
|---|---|---|---|---|
| 1 | ||||
| 2 | ||||
| 3 |
Visitors
| # | Name | Company | Purpose | Time in / out |
|---|---|---|---|---|
| 1 | ||||
| 2 | ||||
| 3 |
Delays, problems and extra work
Safety
Instructions, RFIs, directives and changes
Photos taken
A daily log on your phone, with photos
Arazim Reports turns your site notes and photos into a clean PDF on your letterhead, filed by project so you can find any day later.
Start free trial 14 days free, no credit card. Then $10/month for your first year.FAQ
What should a construction daily log include?
Date, weather (morning and afternoon), manpower by company and trade with hours, equipment on site, work performed by area, deliveries, inspections and tests, visitors, delays and their causes, safety events, and instructions or changes received. Sign and file it the same day.
Who fills out the daily log?
Usually the general contractor's superintendent. Owner's reps, inspectors and subcontractor foremen often keep their own daily records too. Your contract may say who must keep the log and how often it is submitted.
Can I use this daily log template for free?
Yes. Print it, save it as a PDF or type into the fields before printing. No sign-up is needed, and nothing you type is stored or sent anywhere.
How long should I keep daily logs?
Keep them with the project records for as long as your contract, your insurer and your state's rules require. Logs are often requested years later in claims, so many firms keep them well past closeout.
This template is a general working form. It does not replace the requirements of your contract, your building department or your firm's procedures. Adapt it to your project.