Arazim Reports

Guides / Structural observation

Structural observation reports: what the SER includes

Updated October 20, 2026 · 8 min read

Short answer: A structural observation report records a registered design professional's visual review of the structural system for general conformance with the approved construction documents. Under the International Building Code, structural observation is a separate requirement from special inspection: special inspectors verify specific work against specific criteria, while structural observation is a broader look at the system as a whole. A typical report lists the visit date, stage of construction, elements observed, deficiencies and their resolution, and a final statement at the end. When it's required, who may perform it and what form the reports take are set by the code edition your jurisdiction adopted and by the AHJ, so check with your local building department.

This guide is written for structural engineers of record, their field staff, and the owners and contractors who receive these reports. It explains the general framework. It is not a substitute for the code as adopted in your jurisdiction, your building department's requirements, or your contract.

Structural observation vs. special inspection

These two get mixed up constantly, sometimes even on permit documents. They're related, they often happen on the same projects, and they're different things.

Special inspectionStructural observation
PurposeVerify that specific work (welds, bolts, concrete placement, masonry, etc.) meets the approved documents and referenced standardsVisual review of the structural system for general conformance with the approved construction documents
Who performs itA qualified special inspector, often from a testing and inspection agency, approved as the AHJ requiresA registered design professional, commonly the SER or someone under their supervision, as permitted by the code and AHJ
FrequencyContinuous or periodic, per the statement of special inspectionsAt significant construction stages, as set out in the structural observation program
OutputInspection reports and a final report of special inspectionsObservation reports per visit and, at completion, a written statement on observations and deficiencies

Put simply: the special inspector checks that the bolts in this connection are the right grade and properly tensioned. The structural observer looks at whether the lateral system is being built the way it was designed: whether collectors are where they belong, whether a shear wall got shortened by a late door opening, whether load paths make sense.

For what the special inspector's reports must contain, see special inspection reports under IBC Chapter 17.

Neither one replaces the contractor's quality control, and neither makes the observer responsible for means, methods or site safety.

When structural observation is required

The IBC requires structural observation for certain buildings, generally tied to seismic design category, wind exposure and speed, risk category and building height or type. The thresholds and wording have changed between code editions, and many states and cities amend the IBC. Some jurisdictions require structural observation more broadly than the model code. Others have their own forms and registration rules.

So the practical answer is: look at the code edition adopted where the project is, any local amendments, and the building department's published requirements. The SER usually identifies the requirement on the structural drawings, and the permit may list it as a condition. When in doubt, ask the plan reviewer or the AHJ before construction starts, not after the first pour.

Who can perform structural observation

Usually a registered design professional, often the engineer of record for the structure or someone the owner engages. Some jurisdictions require the observer to be the SER or a person under their supervision; some allow another engineer. Many require the owner to engage the observer directly. Check the local rules, and confirm the observer's qualifications are acceptable to the AHJ before the first visit.

What a structural observation report contains

Formats vary by firm and by jurisdiction. Some building departments supply a mandatory form. A complete report generally includes:

Structural observation report outline

  1. Project name, address, permit number
  2. Observer's name, firm, license number and signature
  3. Visit number and date; stage of construction
  4. Elements observed: foundations, framing, lateral system, diaphragms, connections, by level and grid
  5. Construction documents and revisions referenced
  6. Observations, numbered, with location, description and photos
  7. Deficiencies: the condition, the requirement it doesn't meet, and the required response (correction, RFI, or engineered fix)
  8. Status of deficiencies from previous visits
  9. Areas not observed and limitations of the visit
  10. Statement that the observation does not constitute special inspection or relieve the contractor of its obligations (if your firm uses one)
  11. Distribution: owner, contractor, building official as required

The final statement

At the end of the observation program, the IBC framework calls for a written statement to the building official saying whether the observation visits were made and whether any deficiencies observed were resolved. The exact wording, timing and form are often specified locally. Many departments won't issue a certificate of occupancy without it. Track open deficiencies from the first visit so writing this statement doesn't turn into a records hunt.

Writing observations that stand up

Common mistakes

Arazim offers a separate Structural app (early access) with a structural observation letter for this kind of visit, issued as a signed PDF on the firm's letterhead. The engineering judgment, and the responsibility, stay with the engineer. For general visits, see the field report guide; for checklist inspections, the site inspection report template.

Observation reports, signed and filed from the site

Record what you observed, with photos, and issue a signed PDF on your letterhead. Structural is in early access; Field Reports is open now.

Start free trial 14 days free, no credit card. Then $10/month for your first year.

FAQ

What is the difference between structural observation and special inspection?

Special inspection verifies specific work, such as welding, bolting, concrete or masonry, against the approved documents and standards, and is performed by a qualified special inspector. Structural observation is a visual review of the structural system as a whole for general conformance, performed by a registered design professional. Requirements vary by jurisdiction.

Is structural observation required on my project?

It depends on the code edition and amendments adopted by your jurisdiction and on the building's characteristics, such as seismic design category, wind conditions, risk category and height. The structural drawings or permit conditions usually say so. Confirm with your local building department.

Who can perform structural observation?

Generally a registered design professional, often the structural engineer of record or someone under their supervision. Some jurisdictions have additional rules about who qualifies and who must engage the observer. Check with the AHJ before construction starts.

What goes in the final structural observation statement?

Typically a written statement to the building official that the required observation visits were made and whether observed deficiencies were resolved. Many jurisdictions specify the form or wording, and the statement may be needed before a certificate of occupancy is issued.

Does structural observation make the engineer responsible for the contractor's work?

Structural observation is generally not intended to guarantee the contractor's work or cover means, methods or site safety. Exact responsibilities depend on the code, your contract and state law. This guide is not legal advice.