Guides / Special inspection
Special inspection reports under IBC Chapter 17
Short answer: IBC Chapter 17, "Special Inspections and Tests," requires certain work to be inspected by a qualified special inspector from an approved agency, hired by the owner or the owner's agent. The design professional in responsible charge lists the required inspections in a statement of special inspections that goes in with the permit application. The agency keeps records and reports to the building official and the design professional. Discrepancies go to the contractor first, then to the building official and the design professional if they aren't corrected. At the end, a final report documents the inspections and the correction of discrepancies. Your jurisdiction may use a different code edition, amendments and its own forms, so check with the building department.
This guide is written for special inspectors, the engineers who write the statement of special inspections, and the owners and contractors who live with the results. Section numbers below follow the 2021 International Building Code. Other editions, and state and city codes based on the IBC, number some sections differently or change the requirements. It is general information, not legal or engineering advice.
What special inspection is, and what it isn't
Special inspection is inspection of construction that needs the expertise of a qualified special inspector, on top of the building department's own inspections. The special inspector works for an approved agency and checks specific work, such as reinforcing steel placement, welds, high-strength bolting, masonry grouting or fill compaction, against the approved construction documents and the referenced standards.
The code defines two frequencies (Section 202), and the statement of special inspections assigns one to each item:
- Continuous: the special inspector is present when and where the work is being performed.
- Periodic: the special inspector is present intermittently where the work has been or is being performed.
Special inspection is not the contractor's quality control, and it is not structural observation. Structural observation (Section 1704.6) is the design professional's visual review of the structural system for general conformance. The two often happen on the same project and they're reported separately.
Who does what
| Party | Role under Chapter 17 (2021 IBC) |
|---|---|
| Owner, or the RDP in responsible charge acting as the owner's agent | Employs one or more approved agencies to perform the special inspections and tests (Section 1704.2). |
| Registered design professional in responsible charge (RDPiRC) | Prepares the statement of special inspections, submitted with the permit application (Sections 1704.2.3 and 1704.3). Receives the agency's reports. |
| Approved agency and special inspector | Provides written documentation of the inspectors' competence and experience to the building official (Section 1704.2.1). Keeps records, issues reports, reports discrepancies and submits the final report (Section 1704.2.4). |
| Contractor | Where wind- or seismic-force-resisting systems require special inspection, submits a written statement of responsibility acknowledging the special requirements before starting that work (Section 1704.4). Corrects discrepancies. |
| Building official | Approves the agency and inspectors, receives the reports, and agrees when the final report is due. |
The statement of special inspections
Everything in the field follows from this document. The RDP in responsible charge lists the materials, systems and elements that need special inspection or testing, whether each is continuous or periodic, and the agency responsible. The required items come mostly from Section 1705. Common ones in the 2021 IBC:
- Structural steel (Section 1705.2), with the quality assurance provisions of AISC 360
- Concrete construction (Section 1705.3 and Table 1705.3): reinforcement placement, anchors, and sampling fresh concrete for strength specimens, slump, air content and temperature
- Masonry (Section 1705.4), using the TMS 402 and TMS 602 quality assurance levels
- Wood construction (Section 1705.5), including high-load diaphragms
- Soils (Section 1705.6 and Table 1705.6): site preparation, excavation, fill placement and compaction
- Driven deep foundations, cast-in-place deep foundations and helical piles (Sections 1705.7 to 1705.9)
- Wind and seismic resistance (Sections 1705.12 and 1705.13), where the design triggers them
- Fire-resistive materials and firestopping, among others (for example, Sections 1705.15 and 1705.18)
Each of these has exceptions and thresholds, and Section 1705.1.1 lets the building official require special inspection of other work. Read the statement for your project, not a generic list.
What goes in a daily special inspection report
The code says what the reports must do, not what they look like. Section 1704.2.4 requires the reports to indicate that the work inspected or tested was or was not completed in conformance with the approved construction documents. Most agencies and many building departments have their own forms. A complete field report usually covers:
Special inspection report outline
- Project name, address and permit number
- Agency name, inspector's name and certification (for example, the ICC or other certification your jurisdiction accepts)
- Date, arrival and departure times, weather where it matters (concrete, coatings, welding)
- Item from the statement of special inspections, with continuous or periodic frequency
- Location: level, grid lines, element marks
- Documents used: drawing sheets and revision, approved shop drawings, mix design, WPS
- What was inspected and how: measurements, test results, sample numbers
- Conformance statement: in conformance, or not, with the approved construction documents
- Discrepancies: the condition, the requirement it doesn't meet, who was told and when
- Status of discrepancies from earlier reports
- Photos, numbered and referenced
- Inspector's signature and date; distribution to the building official and the RDPiRC
Writing discrepancies
The discrepancy path in Section 1704.2.4 is simple: bring it to the contractor's immediate attention for correction; if it isn't corrected, bring it to the building official and the RDP in responsible charge before that phase of work is completed. The report should make that path visible.
| Weak entry | Clear entry |
|---|---|
| Rebar not per plans | Level 2 slab, grids C–D/3–4: bottom bars spaced approx. 16 in. o.c.; S-201 calls for #5 @ 12 in. o.c. Reported to GC super (name) at 10:40 AM. Pour on hold for this bay pending correction. |
| Bad weld | Beam B-14 to column C-7, north flange: visible undercut along approx. 3 in. of fillet weld. Reported to erector foreman at 2:15 PM. Reinspect after repair. |
| Compaction failed | Building pad, test location 6: field density 89% vs. 95% specified (geotechnical report). Contractor to rework and retest. |
Keep the language factual. "Not in conformance with S-201" says what the code asks the report to say. "Unacceptable" or "dangerous" goes beyond the inspection.
The final report
Section 1704.2.4 also calls for a final report documenting the required special inspections and tests, and the correction of any discrepancies noted. The model code has it submitted at a point agreed between the owner (or the owner's agent) and the building official before work starts. In practice, many building departments won't issue a certificate of occupancy until they've accepted it.
The final report is easy when every discrepancy was tracked to closure in the daily reports. It is painful when a discrepancy from month two was fixed but never documented. Close discrepancies in writing, with a reinspection date and a photo, as you go.
Common mistakes
- Reports that say what was inspected but not whether it conformed.
- No drawing revision, so nobody can tell which documents the inspector used.
- Discrepancies reported by phone and never written down, or written down and never closed.
- Periodic items inspected after they were covered.
- Reports going only to the contractor, when the building official and the RDP in responsible charge must receive them.
- Using a generic checklist instead of the project's statement of special inspections.
Check your jurisdiction
States and cities adopt different IBC editions and amend Chapter 17. California, for example, publishes its own Chapter 17 in the California Building Code, and New York City has its own building code and special inspection program. Many departments publish a special inspection manual, mandatory forms, inspector registration rules and deadlines for submitting reports. Read those first. This guide is not legal advice and doesn't replace the code as adopted where your project is.
Arazim Reports is a documentation tool. It doesn't replace your agency's required forms or your jurisdiction's procedures. Where your agency allows it, you can use it for the field record: numbered items with a location and photos, a checklist inspection such as the pre-pour inspection (early access), and a signed PDF on your letterhead. For the reports you write as an observer, see the field report guide and the free field report template.
Inspection records with photos, filed by project
Numbered items with a location, a status and photos, and a signed PDF on your letterhead. Pre-Pour Inspection is in early access; Field Reports is open now.
Start free trial 14 days free, no credit card. Then $10/month for your first year.FAQ
What is a special inspection under the IBC?
Special inspection is inspection of certain construction work by a qualified special inspector working for an approved agency, in addition to the building department's own inspections. IBC Chapter 17 lists the work that requires it, such as structural steel, concrete, masonry, certain wood construction, soils and deep foundations, and sets out who hires the agency and how results are reported.
Who receives special inspection reports?
In the 2021 IBC (Section 1704.2.4), the approved agency keeps records of special inspections and tests and submits reports to the building official and to the registered design professional in responsible charge. Many jurisdictions add their own distribution, forms and deadlines.
What happens when a special inspector finds a discrepancy?
Under the model code, discrepancies are brought to the immediate attention of the contractor for correction. If they are not corrected, they are brought to the attention of the building official and the registered design professional in responsible charge before that phase of the work is completed.
What is the final report of special inspections?
A report documenting the required special inspections and tests and the correction of any discrepancies noted. The model code has it submitted at a point agreed before work starts; many building departments require it before they issue a certificate of occupancy.
Who hires the special inspector?
The IBC places this on the owner, or the registered design professional in responsible charge acting as the owner's agent, who employs one or more approved agencies. Check your jurisdiction for added rules on independence and approval of the agency.
Is special inspection the same as structural observation?
No. Special inspection verifies specific work against the approved construction documents and referenced standards. Structural observation is a visual review of the structural system for general conformance, by a registered design professional. They are separate requirements in Chapter 17.